The following is the current operational status of Fukushima Daiichi
Nuclear Power Station subsequent to the aftershock that occurred at
2:07 pm, April 12, 2011:
The maximum seismic acceleration was observed to be 37.3 gal at the
basement mat of the reactor building of Unit 6.
Influence of radioactivity outside: None
The figures of the monitoring posts at the station boundary are within
the usual range, and there is no outside radioactive influence as of now.