Kashiwazaki Kariwa Nuclear Power Station Plant condition after the earthquake (as of 0:15 pm, Second release)
Regarding the earthquake yesterday at 11:32 pm, the operation status at
Kashiwazaki Kariwa Nuclear Power Station at 0:15 today is as follows:

The maximum acceleration of the earthquake that was monitored within the station was at Unit 6 reactor building base at 4.0 Gal. Influence of radioactivity outside: None (as of 0:15) The figures indicated at exhaust stack monitors and monitoring posts at the station boundary are within the usual range, and there is no influence of radioactivity outside as of now. We are currently conducting an inspection for each unit.