search



Corporate Information

 
Press Release (Apr 05,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 7:00 PM, April 5)
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12th. It was assumed to be hydrogen 
 explosion.
-At approximately 2:30 am on March 23rd, seawater injection to the 
 nuclear reactor through the feed water system was initiated.
-At approximately 10:50 am on March 24th, white fog-like steam arising 
 from the roof part of the reactor building was observed.
-We had been injecting seawater into the reactor, but from 3:37 pm on 
 March 25th, we started injecting freshwater.
-We had been injecting fresh water to the reactor using fire engines; 
 however we switched over utilizing temporary electrical pump at 8:32 
 am on March 29th.
-Some of turbine building lights were turned on April 2nd. 
-We injected fresh water to the reactor by a temporary motor driven pump, 
 but, from 10:42am to 11:52am on April 3rd we temporarily switched the 
 pump to the fire fighting pump to inject fresh water to use power through 
 off-site transmission line. We're now injecting fresh water to the 
 reactor by a motor driven pump powered by off-site transmission line. 
Unit 2(Shut down) 
-At approximately 6:00 am on March 15th, an abnormal noise began emanating 
 from nearby Pressure Suppression Chamber and the pressure within the 
 chamber decreased. 
-We have been injecting seawater into the reactor, but from 10:10 am on 
 March 26th, we started injecting freshwater (with boric acid).
-We had been injecting fresh water in to the reactor utilizing fire pump, 
 however, we switched over to utilizing temporary electrical pump from 
 6:31 pm on March 27th. 
-Some of turbine building lights were turned on April 2nd. 
-We injected fresh water to the reactor by a temporary motor driven pump, 
 but, from 10:22am to 0:06pm on April 3rd, we temporarily switched the 
 pump to the fire fighting pump to inject fresh water to use power through 
 off-site transmission line. We're now injecting fresh water to the 
 reactor by a motor driven pump powered by off-site transmission line. 
Unit 3(Shut down) 
-Explosive sound and white smoke were confirmed at 11:01am March 14th. It 
 was assumed to be hydrogen explosion.
-We had been injecting seawater into the reactor pressure vessel, but from 
 6:02 pm on March 25th, we started injecting freshwater.
-We had been injecting fresh water in to the reactor utilizing fire pump, 
 however, we switched over to utilizing temporary electrical pump from 
 8:30 pm on March 28th.
-Some of turbine building lights were turned on April 2nd. 
-We injected fresh water to the reactor by a temporary motor driven pump, 
 but, from 10:03am to 0:16pm on April 3rd, we temporarily switched the 
 pump to the fire fighting pump to inject fresh water to use power through 
 off-site transmission line. We're now injecting fresh water to the 
 reactor by a motor driven pump powered by off-site transmission line. 
Unit 4 (outage due to regular inspection) 
-At approximately 6 am on March 15th, we confirmed the explosive sound and 
 the sustained damage around the 5th floor rooftop area of the Nuclear 
 Reactor Building.
-Some of turbine building lights were turned on March 31st .
-At this moment, we do not consider any reactor coolant leakage inside the 
 reactor happened. 
Unit 5 (outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5 am, March 19th, we started the Residual Heat Removal System Pump (C) 
 in order to cool the spent fuel pool.
-At 2:30 pm, March 20th, the reactor achieved reactor cold shutdown. At 
 around 5:24 pm on March 23rd, when we switched the temporary Residual 
 Heat Removal System Seawater Pump, it has stopped automatically. At 
 around 4:14 pm, March 24th we replaced the pump, and restarted cooling 
 of reactor at around 4:35 pm.
-At this moment, we do not consider any reactor coolant leakage inside 
 the reactor happened. 
Unit 6 (outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm, March 19th, we started the Residual Heat Removal System 
 Pump (B) of Unit 6 in order to cool the spent fuel pool.
-At 7:27 pm, March 20th, the reactor achieved reactor cold shutdown.
-In relation to the two seawater side pumps of the Residual Heat Removal 
 System, we switched the power source from temporary to permanent at 3:38 
 PM and 3:42PM, Mar 25 respectively.
-At this moment, we do not consider any reactor coolant leakage inside 
 the reactor happened. 
·Operation for cooling the spent fuel pools 
-Water spray by the concrete pump truck to Unit 4 was conducted from 5:35 
 pm to 6:22 pm on April 5th. 
-We will conduct further water spray depending on the conditions of spent 
 fuel pools. 
·Draining water from underground floor of turbine buildings 
-At 1:55 pm April 3rd, in Unit 1, water transfer from a condensate storage 
 tank to a suppression pool water surge-tank was initiated.
-At 5:10 pm, April 2nd, in Unit 2, water transfer from a condensate 
 storage tank was to a suppression pool water surge-tank was initiated. 
Others 
-We measured radioactive materials (iodine etc.) inside of the nuclear 
 power station area (outdoor) by monitoring car and confirmed that 
 radioactive materials level is getting higher than ordinary level. As 
 listed below, we have determined that specific incidents stipulated in 
 article 15, clause 1 of Act on Special Measures Concerning Nuclear 
 Emergency Preparedness (Abnormal increase in radiation dose measured 
 at site boundary) have occurred.
 · Determined at  4:17 pm Mar 12th (Around Monitoring Post 4 )
 · Determined at  8:56 am Mar 13th (Around Monitoring Post 4 )
 · Determined at  2:15 pm Mar 13th (Around Monitoring Post 4 )
 · Determined at  3:50 am Mar 14th (Around Monitoring Post 6 )
 · Determined at  4:15 am Mar 14th (Around Monitoring Post 2 ) 
 · Determined at  9:27 am Mar 14th (Around Monitoring Post 3 ) 
 · Determined at  9:37 pm Mar 14th (Around main entrance ) 
 · Determined at  6:51 am Mar 15th (Around main entrance ) 
 · Determined at  8:11 am Mar 15th (Around main entrance ) 
 · Determined at  4:17 pm Mar 15th (Around main entrance ) 
 · Determined at 11:05 pm Mar 15th (Around main entrance )
 · Determined at  8:58 am Mar 19th (Around MP5)
 From now on, if the measured figure fluctuates and goes above and below 
 500 micro Sv/h, we deem that as the continuous same event and will not 
 regard that as a new specific incidents stipulated in article 15, clause 
 1 of the Act on Special Measures Concerning Nuclear Emergency 
 Preparedness (Abnormal increase in radiation dose measured at site 
 boundary) has occurred. In the interim, if we measure a manifestly 
 abnormal figure and it is evident that the event is not the continuous 
 same event, we will determine and notify.

-The national government has instructed evacuation for those local 
 residents within 20km radius of the periphery and evacuation to inside 
 for those residents from 20km to 30km radius of the periphery, because 
 it is possible that radioactive materials are discharged.
-In total 12 fire engines are lent for the water spraying to the spent 
 fuel pools and water injection to the nuclear reactors by various 
 regional fire departments* as well as Tokyo Fire Department. Also, 
 instruction regarding the setting and operation of large scale 
 decontamination system was provided by Niigata City Fire Headquarter 
 and Hamamatsu City Fire Headquarter.
 *: Koriyama Fire Department, Iwaki Fire Brigade Headquarters, Fire 
 Headquarters of Sukagawa District Wide Area Fire-fighting Association, 
 Yonezawa City Fire Headquarters, Utsunomiya City Fire Headquarters, 
 Fire Headquarters of Aizu-Wakamatsu wide area municipal association, 
 Saitama City Fire Bureau, and Niigata City Fire Bureau.
-By March 22nd, Units 1 through 6 started to be energized from the 
 external power source.
-At around 11:35 am April 1st, a worker fell into the sea when he got 
 into a barge of the U.S. Forces to repair a hose of the ship. The worker 
 was rescued immediately, and was not injured and not contaminated. The 
 worker will be checked using the whole-body counter to ensure his health.
-From April 4th, we began to transfer the radioactive water we collected 
 from the building of Radioactive Waste Treatment Facilities to the Unit 
 4 turbine building. On April 4th, water level of the pit in the trench 
 of Unit 3 increased by 15cm from previous day. Pathway of water flow is 
 unknown. We can not deny the possibility that water in the turbine 
 building of Unit 4 flows into the trench of Unit 3. So, we stopped 
 transferring water to the Unit 4 turbine building to make assurance. 
 Present water level of the pit in the trench of Unit 3 is not changed 
 from the time we stopped transferring, and is being stable.
-At around 9:30 am, April 2nd, we detected water containing radiation dose 
 over 1,000 mSv/h in the pit* where supply cables are stored near the 
 intake channel of Unit 2. Furthermore, there was a crack about 20 cm on 
 the concrete lateral of the pit, from where the water in the pit was out 
 flowing into the sea. (previously announced). 
-We also injected fresh concrete to the pit, but we could not observe a 
 reduction in the amount of water spilling from the pit to the sea. 
 Therefore, we started to inject the polymer (April 3rd). 
-From 7:08 am to 7:11 am on April 4th, we put the tracer into the pit and 
 began an investigation of water flows. Additional tracer was put through 
 the two new holes drilled near the pit. At 2:15 pm, April 5th, it was 
 observed the water with tracer came out from the crack on the concrete 
 lateral of the pit. At 3:7 pm, April 5th, injection of coagulant from the 
 holes was initiated. 
-There is plenty of radioactive wastewater in the turbine buildings. 
 Especially, Unit 2's wastewater is very highly radioactive. To store this 
 stably, it was decided that this needed to be transferred to the Central 
 Radioactive Waste Disposal Facility. However, within that facility, we 
 are storing ten thousand tons of low level radioactive wastewater. In 
 order to transfer more wastewater, we need to discharge the low level 
 radioactive wastewater. In addition, as low radioactive subsurface water 
 is piling up in sub-drain pits of Units 5 and 6 and a part of subsurface 
 water is running into buildings. We are concerned that important 
 equipment to secure the safety of reactors may be submerged. Based on 
 the Section 1 of the Article 64 of the Nuclear Reactor Regulation Law, 
 we have decided to discharge to the sea approximately ten thousand tons 
 of the accumulated low level radioactive water and a total of fifteen 
 hundred tons of the low level radioactive subsurface water stored in the 
 sub drain pits of Unit 5 and 6 as soon as we get ready.
-We evaluate the impact on the discharge of the low radioactive wastewater 
 to the sea as approximately 0.6 mSv per year per an adult if an adult 
 eats adjacent fish and seaweeds everyday. The amount (0.6 mSv of 
 effective radioactive doses per year) is one-forth of annual radioactive 
 dose to which the general public is exposed from nature.
-At 7:03 pm, April 4th, discharge of low radioactive wastewater 
 (approximately 10,000 ton in total) from Central Radioactive Waste 
  Disposal Facility to the sea was initiated. 
-At 9:00 pm, April 4th, discharge of low radioactive subsurface water 
 (1,500 ton in total) from sub-drain pits of Units 5 and 6 to the sea was
  initiated. 
back to page top


to TOP