We are announcing the status of major inspections and restoration works
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Please be advised that we have been temporarily suspending a part of the
restoration works since March 11, 2011, as we have been fully dedicated
to the support and cooperation to Fukushima Daiichi Nuclear Power
Station and Fukushima Daini Nuclear Power Station which were damaged by
the Tohoku-Chihou-Taiheiyo-Oki Earthquake. We resume restoration works
of Kashiwazaki-Kariwa Nuclear Power Station from March 22, 2011
accordingly.
Inspection/ Restoration Status
◇ Inspection and restoration completed between March 25 to March 31,
2011
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between April 1 to April
7, 2011
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from March 27 to
April 23, 2011
- Work Schedule of the Main Inspection/ Restoration of the
Kashiwazaki-Kariwa Nuclear Power Station in Response to the
Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) ... Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported
from March 24 to March 30, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from March 24 to March 30, 2011>
◇ Other Findings
- No notable activity during this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 88.3KB)