Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm March 26th)
[No update from the last release issued at 9:00 am, March 26th]

Unit Status
1    ·Reactor cold shutdown, stable water level, offsite power is 
      available.
     ·No reactor coolant is leaked to the reactor containment vessel.
     ·Maintain average water temperature below 100°C in the Pressure 
      Suppression Chamber.
2    ·Reactor cold shutdown, stable water level, offsite power is 
      available.
     ·No reactor coolant is leaked to the reactor containment vessel.
     ·Maintain average water temperature below 100°C in the Pressure 
      Suppression Chamber.
3    ·Reactor cold shutdown, stable water level, offsite power is 
      available.
     ·No reactor coolant is leaked to the reactor containment vessel.
     ·Maintain average water temperature below 100°C in the Pressure 
      Suppression Chamber.
4    ·Reactor cold shutdown, stable water level, offsite power is 
      available.
     ·No reactor coolant is leaked to the reactor containment vessel.
     ·Maintain average water temperature below 100°C in the Pressure 
      Suppression Chamber.  
Other N.A. 