Press Release (Mar 25,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 0:30 PM Mar 25th)
*new items are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1(Shut down) 
- Reactor has been shut down. However, the explosive sound and white smoke 
  were confirmed after the big quake occurred at 3:36 pm Mar 12th. It was 
  assumed to be hydrogen explosion.
- At approximately 2:30 am on March 23rd, seawater was started to be 
  injected to the nuclear reactor through the feed water system.
- At approximately 10:50 am on March 24th, white fog-like steam arising 
  from the roof part of the reactor building was observed.
- At approximately 11:30 am on March 24th, lights in the main control room 
  was restored. 
- We have been injecting sea water into the reactor pressure vessel. 
Unit 2(Shut down) 
- At approximately 6:00 am on March 15th, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within this 
  chamber decreased. 
- At 6:20 pm on March 21st, white smoke was confirmed arising from the top 
  of the reactor building. As of 7:11 am on March 22nd, smoke decreased to 
  the level where we can hardly confirm
- We have been injecting sea water into the reactor pressure vessel.
 
Unit 3(Shut down) 
- Reactor has been shut down. However, the explosive sound and white 
  smoke were confirmed at 11:01am Mar 14th. It was assumed to be hydrogen 
  explosion.
- At 8:30am on March 16th, fog like steam was confirmed arising from the 
  reactor building.
- At approximately 6:15 am on March 17th the pressure of the Suppression 
  Chamber has temporarily increased. We were preparing to implement a 
  measurement to reduce the pressure of the reactor containment vessel 
  (partial discharge of air containing radioactive material to outside) 
  in order to fully secure safety. However, at present, it is not a 
  situation to take a measure immediately to discharge air containing 
  radioactive material to outside now. We will continue to monitor the 
  status of the pressure of the reactor containment vessel.
- At approximately 4:00 pm, March 21st, light gray smoke was confirmed 
  arising from the floor roof of the Unit 3 building. On March 22nd, 
  the color of smoke changed to somewhat white and it is slowly 
  dissipating.
- At approximately 10:45 pm on March 22nd, the light in the main control 
  room was turned on.
- At around 4:20 pm on March 23rd, our staff confirmed light black smoke 
  belching from the Unit 3 building. At approximately 11:30 pm on March 
  23rd and 4:50 am on March 24th, our employee found no signs of smoke.
- We have been injecting sea water into the reactor pressure vessel. 
Unit 4 (outage due to regular inspection) 
- Reactor has been shut down. However, at approximately 6 am on March 
  15th. We have confirmed the explosive sound and the sustained damage 
  around the 5th floor rooftop area of the Nuclear Reactor Building.
- On March 15th and 16th, we respectively confirmed the outbreak of fire 
  at the 4th floor of the northwestern part of the Nuclear Reactor 
  Building. We immediately reported this matter to the fire department 
  and the related authorities. TEPCO employees confirmed that each fire 
  had already died down by itself. 
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor containment vessel happened. 
Unit 5 (outage due to regular inspection) 
- Reactor has been shut down and the sufficient level of reactor coolant 
  to ensure safety is maintained.
- At 5 am, March 19th, we started the Residual Heat Removal System Pump 
  (C) in order to cool the spent fuel pool.
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor containment vessel happened.
- At 2:30 pm, March 20th, the reactor achieved reactor cold shutdown. At 
  around 5:24 pm on March 23rd, when we switched the temporary Residual 
  Heat Removal System Seawater Pump, it has stopped automatically. At 
  around 4:14 pm, March 24th, we started replaced pump and at around 
  4:35 pm, cooling of reactor has restarted. 
Unit 6 (outage due to regular inspection) 
- Reactor has been shut down and the sufficient level of reactor coolant 
  to ensure safety is maintained.
- We are working on receiving external power supply to Units 5 and 6. We 
  completed the repair work on the emergency diesel generator (A).
- At 10:14 pm, March 19th, we started the Residual Heat Removal System Pump
  (B) of Unit 6 in order to cool the spent fuel pool.
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor containment vessel happened.
- At 7:27 pm, March 20th, the reactor achieved reactor cold shutdown. 
Today's work for cooling the spent fuel pools 
- At approximately 6:05 am, March 25th, we started injecting seawater into 
  the fuel spent pool of Unit 4, using Fuel Pool Cooling and Filtering 
  (clean up) system (FPC) and finished at 10:20 am. At approximately 
  10:30 am, March 25th, we started injecting seawater into the fuel spent 
  pool of Unit 2, using Fuel Pool Cooling and Filtering(clean up) system 
  (FPC). 
- We are considering further spraying at other units and others subject to
  the conditions of spent fuel pools. 
Casualty 
- 2 workers of cooperative firm were injured at the occurrence of the 
  earthquake, and were transported to the hospital on March 11th.
- 4 workers were injured and transported to the hospital after explosive 
  sound and white smoke were confirmed around the Unit 1on March 11th.
- Presence of 2 TEPCO employees at the site is not confirmed on March 11th.
- 1 TEPCO employee who was not able to stand by his own holding left chest
  with his hand, was transported to the hospital by an ambulance on March
  12th.
- 1 subcontract worker at the key earthquake-proof building was unconscious
  and transported to the hospital by an ambulance on March 12th.
- The radiation exposure of 1 TEPCO employee, who was working inside the 
  reactor building, exceeded 100mSv and he was transported to the hospital
  on March 12th.
- 2 TEPCO employees felt bad during their operation in the central control
  rooms of Unit 1 and 2 while wearing full masks, and were transferred to
  Fukushima Daini Nuclear Power Station for consultation with a medical 
  advisor on March 13th.
- 11 workers were injured and transported to Fukushima Daini Nuclear Power
  Station etc. after explosive sound and white smoke were confirmed around
  the Unit 3. One of the workers was transported to the FUKUSHIMA Medical
  University Hospital on March 14th.
- At approximately 10 pm on March 22nd, 1 worker who had been working on 
  setting up a temporary power panel in the common pool was injured and 
  transported to Fukushima Daini Nuclear Power Station where the 
  industrial doctor is.
- At approximately 1 am on March 23rd, 1 worker who had been working on 
  transporting a temporary power panel in the common pool was injured and 
  transported to Fukushima Daini Nuclear Power Station where the 
  industrial doctor is.
- On March 24th, it was confirmed that 3 workers from cooperative 
  companies who were in charge of cable laying work in the 1st floor and 
  the underground floor of turbine building were exposed to the radiation 
  dose of more than 170 mSv. 2 of them were confirmed that their leg skin 
  were contaminated. Although they were decontaminated, since it is judged
  that there is possibility of beta ray burn injury, they were transferred
  to Fukushima Medical University Hospital. The third person also 
  transferred to National Institute of Radiological Sciences in Chiba 
  Prefecture today (March 25). After medical examination at Fukushima 
  Medical University Hospital, they will be transferred to National 
  Institute of Radiological Sciences in Chiba Prefecture today (March 25). 
  Regarding this event, Fukushima Labour Bureau gave TEPCO verbal 
  instructions.After writing up lessons and future measures, taking 
  comments of Fukushima Labour Bureau to heart, TEPCO will report related 
  government ministries and agencies to make assurance doubly sure 
  thoroughness of radiation control and exposure to radiation. 
  Before today's restoration work, we will make notification to the 
  concerned parties and continue to take all possible measures to 
  future management. 
Others 
- We measured radioactive materials (iodine etc.) inside of the nuclear 
  power station area (outdoor) by monitoring car and confirmed that 
  radioactive materials level is getting higher than ordinary level. As 
  listed below, we have determined that specific incidents stipulated in 
  article 15, clause 1 of Act on Special Measures Concerning Nuclear 
  Emergency Preparedness (Abnormal increase in radiation dose measured at 
  site boundary) have occurred.
 ·Determined at 4:17 pm Mar 12th (Around Monitoring Post 4 )
 ·Determined at 8:56 am Mar 13th (Around Monitoring Post 4 )
 ·Determined at 2:15 pm Mar 13th (Around Monitoring Post 4 )
 ·Determined at 3:50 am Mar 14th (Around Monitoring Post 6 )
 ·Determined at 4:15 am Mar 14th (Around Monitoring Post 2 ) 
 ·Determined at 9:27 am Mar 14th (Around Monitoring Post 3 ) 
 ·Determined at 9:37 pm Mar 14th (Around main entrance ) 
 ·Determined at 6:51 am Mar 15th (Around main entrance ) 
 ·Determined at 8:11 am Mar 15th (Around main entrance ) 
 ·Determined at 4:17 pm Mar 15th (Around main entrance ) 
 ·Determined at 11:05 pm Mar 15th (Around main entrance )
 ·Determined at 8:58 am Mar 19th (Around MP5)
From now on, if the measured figure fluctuates and goes above and below 
500 micro Sv/h, we deem that as the continuous same event and will not 
regard that as a new specific incidents stipulated in article 15, clause 
1 of the Act on Special Measures Concerning Nuclear Emergency Preparedness
(Abnormal increase in radiation dose measured at site boundary) has 
occurred. In the interim, if we measure a manifestly abnormal figure and 
it is evident that the event is not the continuous same event, we will 
determine and notify.

- The national government has instructed evacuation for those local 
  residents within 20km radius of the periphery and evacuation to inside 
  for those residents from 20km to 30km radius of the periphery, because 
  it's possible that radioactive materials are discharged.
- At approximately 10am on March 15th, we observed 400mSv/h at the inland 
  side of the Unit 3 reactor building and 100mSv/h at the inland side of 
  the Unit 4 reactor building.
- At around 10:37 am March 21st, water spraying to common spent fuel pool 
  and finished at 3:30 pm (conducted by TEPCO).
- At around 3:37 pm, March 24th, electricity supply to common spent fuel 
  pool has started from external power source. At around 6:05 pm, fuel 
  pool cooling pump was started to cool the pool.
- We found no signs of abnormal situation for the casks by visual 
  observation during the patrol activity. A detailed inspection is under 
  preparation.
- At Units 5 and 6, in order to prevent hydrogen gas from accumulating 
  within the buildings, we have made three holes on the roof of the 
  reactor building for each unit.
- In total 12 fire engines are lent for the water spraying to the spent 
  fuel pools and water injection to the nuclear reactors by various 
  regional fire departments* as well as Tokyo Fire Department. Also, 
  instruction regarding the setting and operation of large scale 
  decontamination system was provided by Niigata City Fire Headquarter and
  Hamamatsu City Fire Headquarter.
*: Koriyama Fire Department, Iwaki Fire Brigade Headquarters, Fire 
   Headquarters of Sukagawa District Wide Area Fire-fighting Association,
   Yonezawa City Fire Headquarters, Utsunomiya City Fire Headquarters, 
   Fire Headquarters of Aizu-Wakamatsu wide area municipal association, 
   Saitama City Fire Bureau, and Niigata City Fire Bureau.
- Until March 22nd, Units 1 through 6 were started to be energized from 
  the external power source.
- We will continue to take all measures to ensure the safety and to 
  continue monitoring the surrounding environment around the Power Station. 