Plant Status of Fukushima Daini Nuclear Power Station (as of 9:00 pm March 21st)
[No New Developments since 6:00 pm, 21st March]

Unit   Status
1    · Reactor cold shutdown, stable water level, offsite power is 
       available.
     · No cooling water is leaked to the reactor containment vessel.
     · Maintain average water temperature below 100°C in the pressure 
       restraint.
2    · Reactor cold shutdown, stable water level, offsite power is 
       available.
     · No cooling water is leaked to the reactor containment vessel.
     · Maintain average water temperature below 100°C in the pressure 
       restraint.
3    · Reactor cold shutdown, stable water level, offsite power is 
       available.
     · No cooling water is leaked to the reactor containment vessel.
     · Maintain average water temperature below 100°C in the pressure 
       restraint.
4    · Reactor cold shutdown, stable water level, offsite power is 
       available.
     · No cooling water is leaked to the reactor containment vessel.
     · Maintain average water temperature below 100°C in the pressure 
       restraint.   

other  N.A.

[The next information in regard to the plant is planned to be released 
 at 9:00 am, 22nd March.] 