Plant Status of Fukushima Daini Nuclear Power Station (as of 0:00 pm March 20th)
No New Developments since 9:00 am, 20th March

Unit   Status
1      · Reactor cold shutdown, stable water level, offsite power is
         available.
       · No cooling water is leaked to the reactor containment vessel.
       · Maintain average water temperature below 100°C in the pressure
         restraint.
2      · Reactor cold shutdown, stable water level, offsite power is
         available.
       · No cooling water is leaked to the reactor containment vessel.
       · Maintain average water temperature below 100°C in the pressure
         restraint.
3      · Reactor cold shutdown, stable water level, offsite power is
         available.
       · No cooling water is leaked to the reactor containment vessel.
       · Maintain average water temperature below 100°C in the pressure
         restraint.
4      · Reactor cold shutdown, stable water level, offsite power is
         available.
       · No cooling water is leaked to the reactor containment vessel.
       · Maintain average water temperature below 100°C in the pressure
         restraint.   
other  N.A.


The next information in regard to the plant is planned to be released
at 3:00 pm, 20th March. 