We are announcing the status of major inspections and restoration works
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Please be advised that we are temporarily postponing a part of restoration
works because we are now doing full-scale support and cooperation to
Fukushima Daiichi Nuclear Power Station and Fukushima Daini Nuclear Power
Station which were damaged by the Tohoku-Chihou-Taiheiyo-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between March 11 to March 17,
2011
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between March 18 to March
24, 2011
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from March 13 to
April 9, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
March 10 to March 16, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from March 10 to March 16, 2011>
◇ Other Findings
- No notable activity during this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 88.7KB)