We are announcing the status of major inspections and restoration works
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between February 25 to March
3, 2011
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between March 4 to March
10, 2011
(To be commenced on the following date)
- Unit 3 Primary containment vessel closure:
March 3*
- Unit 3 System functional test (Selected control rod insertion
inspection):
March 10
* Work schedule altered this week.
◇ Work Schedule of Major Inspection and Restoration from February 27 to
March 26, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
February 24 to March 2, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from February 24 to March 2, 2011>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 89.3KB)