We are announcing the status of major inspections and restoration works
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between February 11 to February
17, 2011
(Completed on the following date)
- Unit 3 Reactor pressure vessel closure:
February 14, 2011
- Unit 3 Carrying in and installation work of power supply input
transformer of the primary loop recirculation system adjustable
speed drive (A) (B):
February 15, 2011
◇ Inspection and restoration to be commenced between February 18 to
February 24, 2011
(To be commenced on the following date)
- Unit 5 General integration inspection:
February 16, 2011*
* Work schedule added this week.
◇ Work Schedule of Major Inspection and Restoration from February 13 to
March 12, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
February 10 to February 16, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from February 10 to February 16, 2011>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 90.8KB)