We are announcing the status of major inspections and restoration works
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between January 14 to January
20, 2011
(Completed on the following date)
- Unit 2 500kV power cable inspection (Laying cables):
January 20, 2011 (To be completed)
- Unit 3 Main generator inspection:
January 14, 2011
- Unit 5 Functional test for the entire plant (Final evaluation)
January 20, 2011
- Restoration and reinforcement work for the on-site/ outside roads &
slope, etc. (Maintenance work of central soil disposal yard):
January 17, 2011
◇ Inspection and restoration to be commenced between January 21 to
January 27, 2011
(To be commenced on the following date)
- Unit 2 500kV power cable inspection (Voltage application test):
January 21, 2011
◇ Work Schedule of Major Inspection and Restoration from January 16 to
February 12, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
January 13 to January 19, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from January 13 to January 19, 2011>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 90.6KB)