We are announcing the status of major inspections and restoration works
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between December 10 to December
16, 2010
(Completed on the following date)
- Unit 5 Functional test for the entire plant (Functional test of
off-gas treatment system):
December 11
- Unit 5 Functional test for the entire plant (Performance test for
steam turbine (#1)):
December 14
◇ Inspection and restoration to be commenced between December 17 to
December 22, 2010
(To be commenced on the following date)
- Unit 3 System functional test (Partial performance test for steam
turbine (#2)):
December 18
◇ Work Schedule of Major Inspection and Restoration from December 12,
2010 to January 8, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
December 9 to December 15, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from December 9 to December 15, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 91.5KB)