Press Release (Nov 18,2010)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of November 18)
We are announcing the status of major inspections and restoration works 
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station 
after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/ Restoration Status 

 ◇ Inspection and restoration completed between November 12 to November 
    18, 2010 
    (Completed on the following date) 

   - No notable activity during this week. 

 ◇ Inspection and restoration to be commenced between November 19 to 
    November 25, 2010 
    (To be commenced on the following date) 

   - Unit 3 System functional test (Partial interlock functional test of 
     reactor protection system): 
       November 16*

   - Unit 3 System functional test (Functional test of standby liquid 
     control system):
       November 17*

   - Unit 3 System functional test (Functional test of main control room 
     emergency circulation system):
       November 17*

   - Unit 3 System functional test (Functional test of standby gas 
     treatment system):
       November 18*

   - Unit 3 System functional test (Functional test of DC power source 
     system):
       November 19

   - Unit 3 System functional test (Rated capacity verification test for 
     the emergency diesel generator):
       November 24

   - Unit 3 System functional test (Functional test of the emergency diesel 
     generator, high pressure core spray system diesel generator, high 
     pressure core spray system, low pressure core spray system, low 
     pressure flooder system and reactor component cooling water system):
       November 25

   - Unit 5 Functional test for the entire plant: 
       November 17*

                                         * Work schedules added this week.

 ◇ Work Schedule of Major Inspection and Restoration from November 14 to 
    December 11, 2010

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                               ...Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed 
after the Niigata-Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the 
 Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki 
 Earthquake," the Tokyo Electric Power Company, Incorporated (TEPCO) 
 provides this announcement containing incidents information reported from 
 November 11 to November 17, 2010. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from November 11 to November 17, 2010>
Reports from November 11 to November 17, 2010
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
          Earthquake (during 4 Weeks) (PDF 92.2KB)