We are announcing the status of major inspections and restoration works
and non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between October 8 to October
14, 2010
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between October 15 to
October 21, 2010
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from October 10
to November 6, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
October 7 to October 13, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from October 7 to October 13, 2010>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki
Earthquake; Grades GI, GII, GIII; and non-graded)
(including nonconformances related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* By close reexamination of past nonconformance incidents, twenty seven
of them are identified as not related to the Chuetsu-Oki Earthquake,
so the total number of them has been corrected.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 89.8KB)