We are announcing the status of major inspections and restoration works and
non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between September 10 to September
16, 2010
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between September 17 to
September 22, 2010
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from September 12 to
October 9, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) provides
this announcement containing incidents information reported from September 9
to September 15, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from September 9 to September 15, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 90.0KB)