We are announcing the status of major inspections and restoration works and
non conformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after
the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between July 30 to August 5, 2010
(Completed on the following date)
- Unit 1 General integration inspection:
August 4
◇ Inspection and restoration to be commenced between August 6 to August 12,
2010
(To be commenced on the following date)
- No notable activity during this week
◇ Work Schedule of Major Inspection and Restoration from August 1 to August
28, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO) provides
this announcement containing incidents information reported from July 29
to August 4, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from July 29 to August 4, 2010>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki
Earthquake; Grades GI, GII, GIII; and non-graded)
(including nonconformances related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* By close reexamination of past nonconformance incidents, one of them
is identified as not related to the Chuetsu-Oki Earthquake, so the
total number of them has been corrected.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 90.6KB)