Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of July 22)
We are announcing the status of major inspections and restoration works and non conformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status 

 ◇ Inspection and restoration completed between July 16 to July 22, 2010 
    (Completed on the following date) 

   - No notable activity during this week. 

 ◇ Inspection and restoration to be commenced between July 23 to July 29, 2010 
    (To be commenced on the following date) 

   - Unit 2 500kV power cable inspection (Preparation for laying cables):
       July 21* 

   - Unit 2 Seismic reinforcement works (Seismic reinforcement works for the fuel 
     handling machine): 
       July 27 
                                                   * Work schedule altered this week. 

 ◇ Work Schedule of Major Inspection and Restoration from July 18 to August 14, 2010

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from July 15 to July 21, 2010. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from July 15 to July 21, 2010>
Reports from July 15 to July 21, 2010
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 90.4KB)