We are announcing the status of major inspections and restoration works and non conformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between July 2 to July 8, 2010
(Completed on the following date)
- Unit 1 Functional test for the entire plant (Final evaluation):
July 5
◇ Inspection and restoration to be commenced between July 9 to July 15, 2010
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from July 4 to July 31, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from July 1 to July 7, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from July 1 to July 7, 2010>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades GI, GII, GIII; and non-graded)
(including nonconformances related to: the Chuetsu-Oki Earthquake; Grades As,
A, B, C, D; and non-graded)
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 90.5KB)