We are announcing the status of major inspections and restoration works and non conformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between June 25 to July 1, 2010
(Completed on the following date)
- Unit 1 Functional test for the entire plant (Performance test of steam turbine (#1)):
June 24*
- Unit 3 Seismic reinforcement works (Seismic reinforcement works for stack):
June 29
- Unit 4 500kV power cable inspection (Laying cables):
June 30
- Unit 4 Seismic reinforcement works (Seismic reinforcement works for stack):
June 29
◇ Inspection and restoration to be commenced between July 2 to July 8, 2010
(To be commenced on the following date)
- Unit 4 Turbine inspection (High-pressure turbine and low-pressure turbine
(A) (B) (C) restoration work):
July 5
* Work schedule added this week.
◇ Work Schedule of Major Inspection and Restoration from June 27 to July 24, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from June 24 to June 30, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 24 to June 30, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 72.2KB)