We are announcing the status of major inspections and restoration works and non conformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between June 18 to June 24, 2010
(Completed on the following date)
- Unit 1 Functional test for the entire plant (Inspection after reaching rated
thermal output):
June 17*
- Unit 1 Functional test for the entire plant (Functional test for reactor core
isolation cooling system (RCIC)):
June 22
- Unit 1 Functional test for the entire plant (Functional test of off-gas treatment
system):
June 23
- On-site check, inspection and restoration of the oil protection bank for the
transformer (Unit 2 Restoration work):
June 23
◇ Inspection and restoration to be commenced between June 25 to July 1, 2010
(To be commenced on the following date)
- No notable activity during this week.
* Work schedule added this week.
◇ Work Schedule of Major Inspection and Restoration from June 20 to July 17, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from June 17 to June 23, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 17 to June 23, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 71.9KB)