We are announcing the status of major inspections and restoration works and non conformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 
Inspection/Restoration Status 
 ◇ Inspection and restoration completed between June 18 to June 24, 2010 
    (Completed on the following date) 
   - Unit 1 Functional test for the entire plant (Inspection after reaching rated 
     thermal output):
       June 17* 
   - Unit 1 Functional test for the entire plant (Functional test for reactor core 
     isolation cooling system (RCIC)):
       June 22 
   - Unit 1 Functional test for the entire plant (Functional test of off-gas treatment 
     system):
       June 23 
   - On-site check, inspection and restoration of the oil protection bank for the 
     transformer (Unit 2 Restoration work): 
       June 23 
 ◇ Inspection and restoration to be commenced between June 25 to July 1, 2010 
    (To be commenced on the following date) 
   - No notable activity during this week. 
                                                   * Work schedule added this week.
 ◇ Work Schedule of Major Inspection and Restoration from June 20 to July 17, 2010
   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix
(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
 Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
 incidents information reported from June 17 to June 23, 2010. 
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|  |  | 
    <Reports from June 17 to June 23, 2010>
 ◇ Other Findings
   - Nothing to disclose to this week.

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 71.9KB)