We are announcing the status of major inspections and restoration works and non conformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between June 11 to June 17, 2010
(Completed on the following date)
- Unit 1 Functional test for the entire plant (Inspection after generating power
at approx. 75% of the rated output):
June 11
- Unit 1 Functional test for the entire plant (Inspection after generating power
at 100% of the rated output):
June 15
◇ Inspection and restoration to be commenced between June 18 to June 24, 2010
(To be commenced on the following date)
- Unit 2 Seismic reinforcement works (Preparation for seismic reinforcement works
for the fuel handling machine):
June 21
◇ Work Schedule of Major Inspection and Restoration from June 13 to July 10, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from June 10 to June 16, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 10 to June 16, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 72.3KB)