Press Release (Jun 17,2010)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 17)
We are announcing the status of major inspections and restoration works and non conformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status 

 ◇ Inspection and restoration completed between June 11 to June 17, 2010 
    (Completed on the following date) 

   - Unit 1 Functional test for the entire plant (Inspection after generating power 
     at approx. 75% of the rated output):
       June 11

   - Unit 1 Functional test for the entire plant (Inspection after generating power 
     at 100% of the rated output):
       June 15 

 ◇ Inspection and restoration to be commenced between June 18 to June 24, 2010 
    (To be commenced on the following date) 

   - Unit 2 Seismic reinforcement works (Preparation for seismic reinforcement works 
     for the fuel handling machine): 
       June 21 

 ◇ Work Schedule of Major Inspection and Restoration from June 13 to July 10, 2010

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from June 10 to June 16, 2010. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from June 10 to June 16, 2010>
Reports from June 10 to June 16, 2010
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 72.3KB)