We are announcing the status of major inspections and restoration works and non conformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between May 28 to June 3, 2010
(Completed on the following date)
- Unit 1 Functional test for the entire plant (Restarting the nuclear reactor):
May 31
- Unit 1 Functional test for the entire plant (Test of raising the reactor pressure
to approx. 3.5MPa):
June 2
◇ Inspection and restoration to be commenced between June 4 to June 10, 2010
(To be commenced on the following date)
- Unit 4 500kV power cable inspection (Voltage application test):
June 4
◇ Work Schedule of Major Inspection and Restoration from May 30 to June 26, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from May 27 to June 2, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from May 27 to June 2, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 71.9KB)