We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between March 19 to March 25, 2010
(Completed on the following date)
-Unit 2 Core shroud preventive maintenance (Preventive maintenance):
March 22
-Unit 4 Main exhaust duct inspection and restoration (Restoration work):
March 24
◇ Inspection and restoration to be commenced between March 26 to April 1, 2010
(To be commenced on the following date)
- Restoration and reinforcement work for the on-site/ outside roads and slope:
April 1
◇ Work Schedule of Major Inspection/ Restoration from March 21 to April 17, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from March 18 to March 24, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|  |
<Reports from March 18 to March 24, 2010>
◇ Other Findings
- Nothing to disclose to this week.

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 72.6KB)