Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of March 11)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status 

 ◇ Inspection and restoration completed between March 5 to March 11, 2010 
    (Completed on the following date) 

   - No notable activity during this week.

 ◇ Inspection and restoration to be commenced between March 12 to March 18, 2010 
    (To be commenced on the following date) 

   - No notable activity during this week.

 ◇ Work Schedule of Major Inspection/ Restoration from March 7 to April 3, 2010

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from March 4 to March 10, 2010. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from March 4 to March 10, 2010>
Reports from March 4 to March 10, 2010
◇ Other Findings - Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
Other Findings
* Numbers were corrected to reflect nonconformance incidents that had been identified as not related to the Chuetsu-Oki Earthquake (2 cases), additions of nonconformance incidents that had been identified as related to the Chuetsu-Oki Earthquake (2 cases) and an incident that had been double-counted.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 72.5KB)