We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between January 29 to February 4, 2010
(Completed on the following date)
- Unit 3 500kV power cable inspection (Laying cables):
January 29
- High-voltage start-up transformer #2 inspection (Carrying in and installation
work):
February 3
- House boilers inspection (3A Electric boiler transformer carrying in, installation
work and test run)
February 2*1
◇ Inspection and restoration to be commenced between February 5 to February 12, 2010
(To be commenced on the following date)
- Unit 1 System functional test (Performance test for steam turbine #2):
February 4*2
- Unit 1 System functional test (Primary containment vessel leak-rate inspection):
February 8
- Unit 1 System functional test (Performance test for reactor building airtightness):
February 12
- Unit 1 System functional test (Functional test of primary containment vessel spray
system):
February 12
- Unit 2 Core shroud preventive maintenance:
February 8
- Unit 5 Primary containment vessel closure:
February 7
- Unit 5 System functional test (Functional test of control rod drive system):
February 5
- Unit 5 System functional test (Performance test for steam turbine #2):
February 9
- Unit 5 System functional test (Selected control rod insertion inspection):
February 10
*1 Work schedule altered this week.
*2 Work schedule added this week.
◇ Work Schedule of Major Inspection/ Restoration from January 31 to February 27, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from January 28 to February 3, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from January 28 to February 3, 2010>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect a nonconformance incident that had been
identified as not related to the Chuetsu-Oki Earthquake and additions of
nonconformance incidents that had been identified as related to the Chuetsu-Oki
Earthquake (2 cases).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 77.6KB)