We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between January 15 to January 21, 2010
(Completed on the following date)
- Unit 1 Main generator inspection:
January 15
- Unit 6 General integration inspection:
January 19
◇ Inspection and restoration to be commenced between January 22 to January 28, 2010
(To be commenced on the following date)
- Unit 1 Outdoor duct inspection:
January 26
- Unit 1 System functional test (Partial interlock functional test of reactor protection system):
January 22
- Unit 4 500kV power cable inspection (Laying cables):
January 27
- Unit 5 Fuel-load work (Core status confirmation):
January 24
- Unit 5 Reactor pressure vessel closure:
January 26
- Unit 5 Outdoor duct inspection:
January 26
- Unit 5 System functional test (Reactor shut-down margin inspection):
January 25
- Unit 6 General integration inspection:
January 18*
* Work schedule added this week.
◇ Work Schedule of Major Inspection/ Restoration from January 17 to February 13, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from January 14 to January 20, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from January 14 to January 20, 2010>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 78.1KB)