We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between January 8 to January 14, 2010
(Completed on the following date)
- Unit 1 Reactor pressure vessel closure:
January 8
- Unit 1 Circulating water pipe inspection (Foundation improvement, excavating work,
and inspection of pipes):
January 12
- Unit 5 Seismic reinforcement (Seismic reinforcement works for stack):
To be completed on January 14
◇ Inspection and restoration to be commenced between January 15 to January 21, 2010
(To be commenced on the following date)
- Unit 1 System functional test (Functional test of primary containment vessel
isolation valve):
January 19
- Unit 1 System functional test (Functional test of feed water pump):
January 20
- Unit 4 Main exhaust duct inspection and restoration (Restoration work):
January 11*
- Unit 5 Fuel-load work:
January 15
* Work schedules added this week.
◇ Work Schedule of Major Inspection/ Restoration from January 10 to February 6, 2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from January 7 to January 13, 2010.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from January 7 to January 13, 2010>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect nonconformance incidents that had been
identified as not related to the Chuetsu-Oki Earthquake (5 cases).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 78.1KB)