We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between December 18 to December 24, 2009
(Completed on the following date)
- Unit No.1 Fuel-load work (Fuel-load work):
December 18
- Unit No.1 Fuel-load work (Core status confirmation):
December 21
- Unit No.1 Turbine inspection (High-pressure turbine and low pressure turbine
(A) (B) (C) detailed inspection and restoration):
December 19
◇ Inspection and restoration to be commenced between December 25, 2009 to January 7,
2010
(To be commenced on the following date)
- Unit No.1 System functional test (Reactor shut-down margin inspection):
December 20*
- Unit No.1 System functional test (Functional test of control rod drive mechanism):
January 5, 2010
- Unit No.1 System functional test (Functional test of control rod drive system):
January 7, 2010
- General integration inspection:
December 27
* Work schedule altered this week.
◇ Work Schedule of Major Inspection/ Restoration from December 20, 2009 to January 16,
2010
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from December 17 to December 23, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from December 17 to December 23, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 80.8KB)