Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of November 19)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between November 13 to November 19, 2009 
    (Completed on the following date) 

   - No notable activity during this week. 

 ◇ Inspection and restoration to be commenced between November 20 to November 26, 2009 
(To be commenced on the following date) 

   - Unit No.1 Turbine inspection (Restoration of high-pressure turbine and low pressure 
     turbine (A) (B) (C)): 
       November 19* 
   - Unit No.1 System functional test (Functional test of standby liquid control system): 
       November 20 
   - Unit No.1 System functional test (Functional test of main control room emergency 
     circulation system): 
       November 26 
   - Unit No.4 500kV power cable inspection (Preparation for laying cables): 
       November 26 
   - Unit No.5 System functional test (Functional test of flammability control system): 
       November 20 
   - Unit No.5 System functional test (Functional test of primary containment vessel spray
     system): 
       November 23 
   - Unit No.5 System functional test (Rated capacity verification test for emergency diesel
     generator): 
       November 23 
   - Unit No.5 System functional test (Functional test of emergency diesel generator, 
     high pressure core spray system diesel generator, high pressure core spray system,
     low pressure core spray system, low pressure flooder system and reactor component 
     cooling water system): 
       November 26 
   - On-site check, inspection and restoration of the oil protection bank for the transformer
     (Unit No.2 Restoration work):   
       November 17* 
                                                      * Work schedules added this week.

 ◇ Work Schedule of Major Inspection/ Restoration from November 15 to December 12, 2009

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from November 12 to November 18, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake) 
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from November 12 to November 18, 2009>
Reports from November 12 to November 18, 2009
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 73.6KB)