Press Release (Nov 12,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of November 12)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between November 6 to November 12, 2009 
    (Completed on the following date) 

   - Unit No.5 500kV power cable inspection (Voltage application test): 
       November 5* 
   - Unit No.7 Planned shutdown of the unit: 
       November 7 

 ◇ Inspection and restoration to be commenced between November 13 to November 19, 2009 
    (To be commenced on the following date) 

   - Unit No.1 System functional test (Functional test of DC power source system): 
       November 17 
   - Unit No.1 System functional test (Functional test of flammability control system):
       November 18 
   - Unit No.5 System functional test (Functional test of standby liquid control system): 
       November 13 
   - Unit No.5 System functional test (Functional test of DC power source system): 
       November 13 
   - Unit No.5 System functional test (Partial interlock functional test of reactor 
     protection system): 
       November 16 
   - Unit No.5 System functional test (Functional test of automatic depressurization 
     system): 
       November 18 
   - Unit No.5 System functional test (Functional test of standby gas treatment system): 
       November 19 
   - Unit No.5 System functional test (Functional test of instrument compression air 
     system): 
       November 19 
   - Unit No.5 System functional test (Partial interlock functional test for liquid 
     waste storage facility and disposal equipment #1): 
       November 19 
                                                      * Work schedules added this week.

 ◇ Work Schedule of Major Inspection/ Restoration from November 8 to December 5, 2009

   - Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix 

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from November 5 to November 11, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake) 
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from November 5 to November 11, 2009>
Reports from November 5 to November 11, 2009
◇ Other Findings - Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
Other Findings
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) 
                                                                               (PDF 105KB) 