We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between October 16 to October 22, 2009
(Completed on the following date)
- Unit No.3 Turbine inspection (Low-pressure turbine (A) (B) restoration work of
blades):
To be completed on October 22
◇ Inspection and restoration to be commenced between October 23 to October 29, 2009
(To be commenced on the following date)
- Unit No.3 Seismic reinforcement works (Preparation for seismic reinforcement works
for reactor building overhead crane):
October 27
- Unit No.3 Seismic reinforcement works (Preparation for seismic reinforcement works
for the fuel handling machine):
October 26
- Unit No.4 Restoration work of stand-by gas treatment system piping duct substruction
(Restoration work):
October 28*
- Unit No.4 Seismic reinforcement works (Seismic reinforcement works for reactor
building overhead crane):
October 21*
* Work schedules altered this week.
◇ Work Schedule of Major Inspection/ Restoration from October 18 to November 14, 2009
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from October 15 to October 21, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from October 15 to October 21, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 100KB)