We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between October 2 to October 8, 2009
(Completed on the following date)
- Unit No.1 Seismic reinforcement works (Seismic reinforcement works for the fuel
handling machine):
To be completed on October 8
- On-site check/ inspection/ restoration of the oil protection bank for the transformer
(Unit No.1 Restoration work):
October 3
◇ Inspection and restoration to be commenced between October 9 to October 15, 2009
(To be commenced on the following date)
- House boilers inspection (3A Electric boiler transformer carrying in):
October 9
◇ Work Schedule of Major Inspection/Restoration from October 4 to October 31, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from October 1 to October 7, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from October 1 to October 7, 2009>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect a nonconformance incident that had been
identified as not related to the Chuetsu-Oki Earthquake and additions of
nonconformance incidents that had been identified as related to the
Chuetsu-Oki Earthquake (2 cases).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 101KB)