We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between September 11 to September 17, 2009
(Completed on the following date)
- Unit No.6 Functional test for the entire plant (Inspection at 100% rated electric
output):
September 10*
- Unit No.6 Functional test for the entire plant (Inspection after reaching rated thermal
output):
September 14
- Unit No.6 Functional test for the entire plant (Functional test of off-gas treatment
system):
September 15
* Work schedules added and altered this week.
◇ Inspection and restoration to be commenced between September 18 to September 25, 2009
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection/Restoration from September 13 to October 10, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from September 10 to September 16, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from September 10 to September 16, 2009>
◇Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 101KB)