Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of September 3)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between August 28 to September 3, 2009 
    (Completed on the following date) 

   - Unit No.2 Reactor recirculation piping preventive maintenance (Ultrasonic testing):
       September 3 
   - Unit No.5 Seismic reinforcement works (Seismic reinforcement works for reactor 
     building overhead crane):
       August 28 
   - Unit No.6 Functional test for the entire plant (Test of raising the reactor pressure 
     to approx. 3.5MPa):
       August 28 
   - Unit No.6 Functional test for the entire plant (Test of raising the reactor pressure 
     to approx. 7.0MPa):
       August 29 
   - Unit No.6 Functional test for the entire plant (Inspection after activating a main 
     turbine generator):
       August 30 
   - Unit No.6 Functional test for the entire plant (Inspection after temporary main 
     generator synchronization):
       August 31 
   - Unit No.6 Functional test for the entire plant (Inspection after generating power 
     at approx. 20% of the rated output):
       September 2 
   - On-site check, inspection and restoration of the oil protection bank for the 
     transformer (Unit No.4 Restoration work): 
       August 28 

 ◇ Inspection and restoration to be commenced between September 4 to September 10, 2009 
    (To be commenced on the following date) 

   - Unit No.4 House transformer inspection (Carrying in and installation work): 
       September 2* 
   - Unit No.4 Excitation transformer inspection (Carrying in and installation work): 
       September 2* 

                                             * Work schedules added and altered this week.

 ◇ Work Schedule of Major Inspection/Restoration from August 30 to September 26, 2009

    - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
      Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                          ....Appendix*

(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

 Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
 Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
 Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
 information reported from August 27 to September 2, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from August 27 to September 2, 2009>
Reports from August 27 to September 2, 2009
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 103KB)