We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between July 31 to August 6, 2009
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between August 7 to August 20, 2009
(To be commenced on the following date)
- Unit No.3 Main transformer inspection (Carrying in and installation work):
August 10
- Unit No.5 500kV power cable inspection (Laying cables):
August 7
◇ Work Schedule of Major Inspection/Restoration from August 2 to August 29, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from July 30 to August 5, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from July 30 to August 5, 2009>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 122KB)