We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between July 17 to July 23, 2009
(Completed on the following date)
- On-site check, inspection and restoration of the oil protection bank for the transformer
(Unit No.5 Restoration work):
July 17
◇ Inspection and restoration to be commenced between July 24 to July 30, 2009
(To be commenced on the following date)
- Unit No.1 Main exhaust duct inspection and restoration (Restoration work):
July 29
- Unit No.1 Seismic reinforcement works (Unit No.1 and Unit No.2 Seismic reinforcement
works for stack):
July 27*
- Unit No.3 Seismic reinforcement works (Seismic reinforcement works for stack):
July 21*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from July 19 to August 15, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from July 16 to July 22, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from July 16 to July 22, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 97.4KB)