We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between July 10 to July 16, 2009
(Completed on the following date)
- Unit No.1 Seismic reinforcement works (Seismic reinforcement works for the roof truss
of the reactor building):
July 13
◇ Inspection and restoration to be commenced between July 17 to July 23, 2009
(To be commenced on the following date)
- Unit No.1 Seismic reinforcement works (Seismic reinforcement works such as pipe
supports):
July 16*
- Unit No.3 500kV power cable inspection (Laying cables):
July 17
- Unit No.3 Seismic reinforcement works (Seismic reinforcement works for stack):
July 20*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from July 12 to August 8, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from July 9 to July 15, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from July 9 to July 15, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 98.8KB)