We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between June 19th to June 25th, 2009
(Completed on the following date)
- Unit No.7 Functional test for the entire plant (Final evaluation):
June 19th
◇ Inspection and restoration to be commenced between June 26th to July 2nd, 2009
(To be commenced on the following date)
- Unit No.5 500kV power cable inspection (Preparation work for laying cables):
June 29th
- Unit No.5 Seismic reinforcement works (Seismic reinforcement works for stack):
June 23rd*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from June 21st to July 18th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from June 18th to June 24th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 18 to June 24, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 102KB)