Press Release (Jun 25,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of June 25th)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between June 19th to June 25th, 2009 
    (Completed on the following date)

   - Unit No.7 Functional test for the entire plant (Final evaluation): 
       June 19th 

 ◇ Inspection and restoration to be commenced between June 26th to July 2nd, 2009 
    (To be commenced on the following date) 

   - Unit No.5 500kV power cable inspection (Preparation work for laying cables): 
       June 29th 
   - Unit No.5 Seismic reinforcement works (Seismic reinforcement works for stack): 
       June 23rd* 
                                      * Work schedules added and altered this week.

 ◇ Work Schedule of Major Inspection/Restoration from June 21st to July 18th, 2009

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake 
                                                                          ....Appendix*


(Reference) 
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake

Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric 
Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
information reported from June 18th to June 24th, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from June 18 to June 24, 2009>
<Reports from June 18 to June 24, 2009>
◇ Other Findings - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               (PDF 102KB)