1. Forecast of Electricity Supply and Demand
The Tokyo Electric Power Co., Inc. (TEPCO) expects its peak demand of the summer 2009 to be
about 61.00 million kW with the assumption of normal summer temperatures. On the other hand,
as for electricity supply, TEPCO will make efforts to secure additional supply by output
increase operation, utilization of electricity during start-up testing, purchasing extra
electricity from in-house power generators, etc., and it will lead to securement of 67.00
million kW excluding the Kashiwazaki-Kariwa Nuclear Power Station Unit No.1 - Unit No.6 hit
by the Niigata-Chuetsu-Oki Earthquake.
[Forecast for the supply and demand in each month]
2. Additional Electricity Supply