We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between June 5th to June 11th, 2009
(Completed on the following date)
- Unit No.6 Turbine inspection (High-pressure turbine and low-pressure turbine (A) (B)
(C) detailed inspection: Restoration of casing, etc.):
June 10th
- Unit No.7 Functional test for the entire plant (Inspection after reaching rated thermal
output):
June 8th
◇ Inspection and restoration to be commenced between June 12th to June 18th, 2009
(To be commenced on the following date)
- Unit No.2 Reactor recirculation piping preventive maintenance (Preventive maintenance
of branch pipe):
June 15th
- Unit No.2 Seismic reinforcement works (Seismic reinforcement works for the roof truss
of the reactor building):
June 11th*
- Unit No.4 Inspection of power supply input transformer of the primary loop recirculation
system adjustable speed drive (Carrying in and installation work):
June 12th
- Unit No.6 System functional test (Partial interlock functional tests of liquid waste
storage facility and disposal equipment):
June 12th
- Unit No.6 System functional test (Functional tests of feedwater pump):
June 15th
- Unit No.6 System functional test (Functional tests of turbine bypass valve):
June 17th
- Reconstruction of arrestor steel tower on Arahama-side (Reconstruction):
June 15th*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from June 7th to July 4th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from June 4th to June 10th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 4 to June 10, 2009>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
- All work related to carrying out hazardous material, which was commenced on April 2nd,
2009, was completed on June 5th, 2009.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 104KB)