We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between May 29th to June 4th, 2009
(Completed on the following date)
- Unit No.7 Functional test for the entire plant (Inspection after generating power
at approx. 50% of the rated output):
May 29th
- Unit No.7 Functional test for the entire plant (Inspection after generating power
at approx. 75% of the rated output):
June 1st
◇ Inspection and restoration to be commenced between June 5th to June 11th, 2009
(To be commenced on the following date)
- Unit No.1 Seismic reinforcement works (Seismic reinforcement works for reactor building
overhead crane):
June 9th
- Unit No.2 Seismic reinforcement works (Seismic reinforcement works for the roof truss
of the reactor building):
June 8th
- Unit No.5 Main exhaust duct inspection and restoration (Restoration work of duct):
June 8th
- Unit No.6 System functional test (Partial interlock functional tests of reactor
protection system):
June 10th
- Reconstruction of arrestor steel tower on Arahama-side (Reconstruction):
June 10th
◇ Work Schedule of Major Inspection/Restoration from May 31st to June 27th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from May 28th to June 3rd, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from May 28 to June 3, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)