We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between May 15th to May 21st, 2009
(Completed on the following date)
- Unit No.6 Primary containment vessel closure work:
May 20th
- Unit No.7 Functional test for the entire plant (Inspection on raising the reactor pressure
to approx. 7.0MPa):
May 14th
- Unit No.7 Functional test for the entire plant (Inspection after activating a main turbine
generator):
May 15th
- Unit No.7 Functional test for the entire plant (Inspection after temporary main generator
synchronization):
May 20th
◇ Inspection and restoration to be commenced between May 22nd to May 28th, 2009
(To be commenced on the following date)
- Unit No.3 Inspection of power supply input transformer of the primary loop recirculation
system adjustable speed drive (Transformer (B) carrying in and installation work):
May 25th
- Unit No.3 500kV power cable inspection (Preparation work for laying cables):
May 20th*
- Unit No.5 Turbine inspection (High-pressure turbine and low-pressure turbine (A) (B) (C)
detailed inspection):
May 25th
- Unit No.5 Seismic reinforcement works (Seismic reinforcement works for reactor building
overhead crane):
May 28th
- Unit No.6 System functional test (Reactor building airtightness inspection):
May 26th
- Restoration work of filtrate tank and demineralized tank on Arahama-side (Restoration work
of No.1 demineralized tank):
May 26th
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from May 17th to June 13th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from May 14th to May 20th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from May 14 to May 20, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 68.4KB)