We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between May 1st to May 14th, 2009
(Completed on the following date)
- Unit No.6 Turbine inspection (Low-pressure turbine restoration work of blades):
April 29th*
- Unit No.7 Functional test for the entire plant (Restarting the nuclear reactor):
May 9th
- Unit No.7 Functional test for the entire plant (Test of raising the reactor pressure
to approx. 3.5MPa):
May 10th
◇ Inspection and restoration to be commenced between May 15th to May 21st, 2009
(To be commenced on the following date)
- Unit No.2 Seismic reinforcement works (Seismic reinforcement works for the roof truss
of the reactor building):
May 18th
- Unit No.3 500kV power cable inspection (Preparation work for laying cables):
May 18th
- Unit No.4 Seismic reinforcement works (Seismic reinforcement works for the roof truss
of the reactor building):
May 18th
- Unit No.5 House transformer inspection (5A, 5B Carrying in and installation work):
April 25th*
- Unit No.5 Seismic reinforcement works (Seismic reinforcement works for reactor building
overhead crane):
May 20th
- Unit No.6 Turbine inspection (Restoration of casing, etc.):
April 30th*
- Unit No.6 System functional test (Primary containment vessel leak-rate inspection):
May 19th
- Unit No.7 Functional test for the entire plant:
May 8th*
- Restoration and reinforcement work for the on-site and outside roads and slope, etc.
(Maintenance work of the slope in front of sub protection headquarter office):
May 13th*
- Restoration and reinforcement work for the on-site and outside roads and slope, etc.
(Restoration work of Daini Takamachi Bridg):
May 12th*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from May 10th to June 6th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from April 30th to May 13th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from April 30 to May 13, 2009>
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
* Numbers were corrected to reflect nonconformance incidents that had been
identified as not related to the Chuetsu-Oki Earthquake (3 cases).
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 87.7KB)