We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between April 17th to April 23rd, 2009
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between April 24th to April 30th, 2009
(To be commenced on the following date)
- Unit No.5 House transformer inspection (5A, 5B Carrying in and installation):
April 24th
- Unit No.5 Seismic reinforcement works (Seismic reinforcement works such as pipe
supports):
April 27th
- Unit No.5 Seismic reinforcement works (Seismic reinforcement works for the fuel
handling machine):
April 23rd*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from April 19th to May 16th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
Power Company, Incorporated (TEPCO) provides this announcement containing incidents
information reported from April 16th to April 22nd, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from April 16 to April 22, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 99.6KB)