Press Release (Apr 02,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of April 2nd)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between March 27th to April 2nd, 2009 
     (Completed on the following date) 

   - Unit No.4 Main exhaust duct inspection and restoration (Restoration of substruction): 
     March 30th 
   - Unit No.5 Main exhaust duct inspection and restoration (Restoration of substruction): 
     March 30th

 ◇ Inspection and restoration to be commenced between April 3rd to April 9th, 2009 
     (To be commenced on the following date) 

   - Unit No.1 House transformer inspection (1A and 1B Carrying in and installation work): 
       March 30th* 
   - Unit No.1 Excitation transformer inspection (Carrying in and installation work): 
       March 30th* 
   - Unit No.1 Seismic reinforcement works (Preparation for seismic reinforcement works
     for reactor building overhead crane): 
       April 6th 
   - Unit No.5 Seismic reinforcement works (Preparation for seismic reinforcement works
     for reactor building overhead crane): 
       April 6th 
   - Unit No.5 Seismic reinforcement works (Preparation for seismic reinforcement works
     for the fuel handling machine): 
       April 6th 
   - High-voltage start-up transformer #2 inspection (Transportation into the factory): 
       April 8th*
                                              * Work schedules added and altered this week.

 ◇ Work Schedule of Major Inspection/Restoration from March 29th to April 25th, 2009

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                               ....Appendix*

  (Reference) 
  Nonconformances Found in the Inspection and Restoration Works Performed after the Niigata-
  Chuetsu-Oki Earthquake

  Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and 
  Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo Electric
  Power Company, Incorporated (TEPCO) provides this announcement containing incidents 
  information reported from March 26th to April 1st, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake) 
Incidents Information (relating to the Chuetsu-Oki Earthquake)
<Reports from March 26 to April 1, 2009>
Reports from March 19 to March 25, 2009
◇ Other Findings - On March 27th, we received a termination notice from the fire headquarters of Kashiwazaki City regarding the ban of handling fire and hazardous materials that had been in place since March 5th, 2009. The fire headquarters issued the termination notice based on their decision that TEPCO's plan to revamp fire and hazardous material handling works was adequate. As we have reconfirmed work procedures and conducted pre-work safety meetings, we will begin carrying out hazardous material from April 2nd.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) 
                                                                                (PDF 40.5KB) 