We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between March 20th to March 26th, 2009
(Completed on the following date)
- High-voltage start-up transformer #2 inspection (Transportation into the factory):
March 26th
◇ Inspection and restoration to be commenced between March 27th to April 2nd, 2009
(To be commenced on the following date)
- Unit No.1 House transformer inspection (1A and 1B Carrying in and installation work):
March 28th
- Unit No.1 Excitation transformer inspection (Carrying in and installation work):
March 28th
- Unit No.5 Main transformer inspection (Carrying in and installation work):
March 25th*
* Work schedules added and altered this week.
◇ Work Schedule of Major Inspection/Restoration from March 22nd to April 18th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
* Handling of fires and hazardous materials has been banned since March 5th, 2009.
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection and
Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from March 19th to March 25th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
<Reports from March 19 to March 25, 2009>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
(PDF 95.4KB)