We are announcing the status of major inspections and restoration works and nonconformances
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between March 13th to March 19th, 2009
(Completed on the following date)
- Unit No.2 Main generator inspection (Rotor carrying in):
March 18th
◇ Inspection and restoration to be commenced between March 20th to March 26th, 2009
(To be commenced on the following date)
- Unit No.5 Main transformer inspection (Carrying in and installation work):
March 23rd
- High-voltage start-up transformer #2 inspection (Transportation into the factory):
March 26th
◇ Work Schedule of Major Inspection/Restoration from March 15th to April 11th, 2009
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
....Appendix*
* Handling of fires and hazardous materials has been banned since March 5th, 2009.
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed after the
Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the Inspection
and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo
Electric Power Company, Incorporated (TEPCO) provides this announcement containing
incidents information reported from March 12th to March 18th, 2009.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
|
< Reports from March 12 to March 18, 2009 >
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)