We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
 ◇ Inspection and restoration completed between February 20th to February 26th, 2009
   (Completed on the following date) 
   - No notable activity during this week. 
 ◇ Inspection and restoration to be commenced between February 27th to March 5th, 2009
   (To be commenced on the following date)  
   - Unit No.1 500kV power cable inspection (Preparation work for laying cables): 
      March 2nd 
   - Unit No.5 Excitation transformer inspection (Carrying in and installation work): 
      March 2nd 
   - Unit No.6 Primary containment vessel closure: 
      March 5th 
   - Unit No.6 System functional test (Functional test of control rod drive mechanism): 
      February 27th 
   - Unit No.6 System functional test (Functional test of control rod drive system): 
      March 4th 
   - House boilers inspection (3A Preparation for transportation of electric boiler 
     transformer): 
      March 2nd 
 ◇ Work Schedule of Major Inspection/Restoration from February 22nd to March 21st, 2009
   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix
 (Reference) 
   Nonconformances Found in the Inspection and Restoration Works Performed after 
   the Niigata-Chuetsu-Oki Earthquake
   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
   Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
   incidents information reported from February 19th to February 25th, 2009. 
 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
  | 
  < Reports from February 19 to February 25, 2009 >
 ◇ Other Findings
   - Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 96.3KB)