search



Corporate Information

 
Press Release (Feb 19,2009)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of February 19th)
We are announcing the status of major inspections and restoration works and nonconformances 
at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status

 ◇ Inspection and restoration completed between February 13th to February 19th, 2009 
    (Completed on the following date) 

   - Unit No.6 Fuel-load work: 
      February 13th 
   - Unit No.6 Core status confirmation: 
      February 17th 
   - House boiler inspection (2B): 
      February 19th 
   - Installing outdoor fire protection system piping above ground, etc. (Arahama-side: 
     Work on installing fire protection system piping to be above ground): 
      February 17th 

 ◇ Inspection and restoration to be commenced between February 20th to February 26th, 2009 
    (To be commenced on the following date)  

   - No notable activity during this week. 

 ◇ Work Schedule of Major Inspection/Restoration from February 15th to March 14th, 2009

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear 
     Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                           ....Appendix

 (Reference) 
   Nonconformances Found in the Inspection and Restoration Works Performed after 
   the Niigata-Chuetsu-Oki Earthquake

   Based on the "Public Announcement Regarding Nonconformance Found in the Inspection 
   and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake", the Tokyo 
   Electric Power Company, Incorporated (TEPCO) provides this announcement containing 
   incidents information reported from February 12th to February 18th, 2009. 

 ◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
Incidents Information (relating to the Chuetsu-Oki Earthquake)
< Reports from February 12 to February 18, 2009 >
Reports from February 12 to February 18, 2009
◇ Other Findings - Work on installing outdoor fire protection system piping on Arahama-side to be placed above ground that was commenced on April 28th, 2008 was completed on February 17, 2009. All the works on outdoor fire protection system piping to be above ground were completed with work on Ominato-side that had been conducted from March 21st, 2008 to June 27th, 2008.
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear
          Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks)
                                                                                (PDF 94.9KB)


back to page top


to TOP